How long does it take to get a Planning Approval?

  • Writer: Swarup Dutta
    Swarup Dutta
  • Jun 17, 2018
  • 1 min read

How long does it take to get Planning Approval?

It depends on what you are planning to build.

The fastest I experienced was about 4 months- but that is rare now a days.

A beach house my family built as owner builders took 2 years to get planning approval!! why?

The water front acreage was zoned Environmentally Sensitive- with a creek running through, very poor soil condition and the list went on. After two years the zoning changed to General Residential and my lemon turned into a million dollar site. The neighbours were the ones to benefit my hard work. I faced the whole council- from Mayor down to engineers. But I love design and engineering and my data on geotech matters flabbergasted them. Council was relying on assumptions, I presented facts.

The approval allowed us to build the beach house from where we saw migrating whales and the Sydney to Hobart race!

In those days only councils could issue Building Approvals after Town Planning approval.

We designed 6 metre deep screw in foundations ( new stuff then) built a drainage system wrapping around the back to drain water. The very low cost light weight house with a dual occ option or BnB had its structure which could be loosened or tightened depending on the soil movement.

Well we never had to adjust one bolt- so much for Council's engineering conditions. And the building faced storms and an mini tornado with no consequence.

And being an owner builder felt great!

The Beach house that moved with the soil movement


 
 
 

Recent Posts

See All

Comments


* Swarup, our Founder, while consulting to a Property Subdivision firm, developers and architects managed 250+ property subdivision permits.

Swarup Dutta is the owner of this domain name and rebranded the website to give it a personal touch.

Disclaimer & Terms of Engagement

The information provided on this website and within our "Site Verdict" or "Advanced Feasibility" reports is intended as Professional Planning Opinion based on the Victorian Planning Provisions (VPP) and our experience with over 250+ managed approvals.

Please note the following:

  • Preliminary Nature: All yield projections, building envelopes, and feasibility data are preliminary. They are subject to formal site surveys, soil reports, and final architectural drafting.

  • Statutory Authority: While we leverage deep expertise to mitigate risk, the final decision regarding any Planning Permit rests solely with the relevant Local Government Authority (Council) or VCAT.

  • 2026 Costings: Construction estimates and trade rates are based on current 2026 Victorian market benchmarks and are subject to fluctuation based on site-specific complexities and final builder tenders.

  • Professional Advice: This guidance does not constitute legal or financial advice. We recommend all clients consult with a qualified legal practitioner regarding Title Covenants and a financial advisor regarding project funding and tax implications.

AuArchitecture reserves the right to refine project strategies as detailed site data becomes available.

We advise you must seek legal and financial advice prior to making a commitment on any property development venture. The opinions we provide are general in nature.

© Copyright
bottom of page