Childcare Project Cost Distribution Plan

  • Writer: Swarup Dutta
    Swarup Dutta
  • Oct 28, 2025
  • 1 min read

Updated: Jan 24

Childcare Cost distribution chart
Childcare Cost distribution chart

CONSTRUCTION COST PLAN


Childcare Centre – 130 Places (3 Levels, Victoria)

Total GFA: ~2,298 sqm

Car Park: 29 spaces

Site Area: 1,766 sqm


🔹 ELEMENTAL COST BREAKDOWN (2025 ESTIMATE)

Element

Description

Unit Rate (AUD/sqm)

Area / Quantity

Cost (AUD)

% of Total

1. Substructure

Footings, ground slab, retaining walls

$350

780 sqm footprint

$273,000

6.2%

2. Superstructure

Frame (concrete & steel), upper floor slabs

$600

1,518 sqm upper floors

$910,800

20.6%

3. External Envelope

Walls, cladding, glazing, insulation

$650

2,298 sqm GFA

$1,493,700

33.8%

4. Roof

Colorbond/insulated flat roof, gutters

$250

780 sqm footprint

$195,000

4.4%

5. Internal Finishes

Partitions, doors, flooring, ceilings, paint

$500

2,298 sqm

$1,149,000

26.0%

6. Services (Electrical, Hydraulic, Fire, HVAC)

All mechanical, electrical, data & plumbing

$420

2,298 sqm

$965,160

21.8%

7. Fixtures, Fittings & Equipment (FFE)

Kitchen, joinery, cots, lockers, toilets

$280

2,298 sqm

$643,440

14.6%

8. External Works & Play Areas

Landscaping, fencing, play surfaces, soft fall

$310

862 sqm

$267,220

6.0%

9. Car Parking & Driveway

Asphalt, line marking, drainage

$800

29 spaces

$232,000

5.2%

10. Preliminaries, OH&P, Contingency

Builder prelims, supervision, insurance

12%

$669,500

15.2%

TOTAL CONSTRUCTION COST (excl. GST)




$6,798,820

100%

💰 Indicative Construction Rate: ≈ $2,960 / sqm GFA (typical for 3-storey centres in metro Victoria)

🔹 ADDITIONAL ALLOWANCES (OPTIONAL)

Item

Estimate (AUD)

Professional & Statutory Fees (8%)

$540,000

Furniture & Teaching Equipment

$180,000

Contingency (Design + Construction, 5%)

$340,000

TOTAL PROJECT BUDGET (incl. above)

≈ $7.86 million

🔹 COST SUMMARY BY CATEGORY

Category

Cost (AUD)

%

Building Construction

$6.80 M

86%

External Works & Carpark

$0.50 M

6%

Fees & Contingencies

$0.56 M

8%

TOTAL PROJECT COST

$7.86 M

100%


 
 
 

Recent Posts

See All

Comments


Swarup Dutta is the owner of this domain name and rebranded the website to give it a personal touch.

* Swarup, our Founder, while consulting to a Property Subdivision firm, developers and architects managed 250+ property subdivision permits.

Disclaimer & Terms of Engagement

The information provided on this website and within our "Site Verdict" or "Advanced Feasibility" reports is intended as Professional Planning Opinion based on the Victorian Planning Provisions (VPP) and our experience with over 250+ managed approvals.

Please note the following:

  • Preliminary Nature: All yield projections, building envelopes, and feasibility data are preliminary. They are subject to formal site surveys, soil reports, and final architectural drafting.

  • Statutory Authority: While we leverage deep expertise to mitigate risk, the final decision regarding any Planning Permit rests solely with the relevant Local Government Authority (Council) or VCAT.

  • 2026 Costings: Construction estimates and trade rates are based on current 2026 Victorian market benchmarks and are subject to fluctuation based on site-specific complexities and final builder tenders.

  • Professional Advice: This guidance does not constitute legal or financial advice. We recommend all clients consult with a qualified legal practitioner regarding Title Covenants and a financial advisor regarding project funding and tax implications.

AuArchitecture reserves the right to refine project strategies as detailed site data becomes available.

We advise you must seek legal and financial advice prior to making a commitment on any property development venture. The opinions we provide are general in nature.

© Copyright
bottom of page