top of page

Childcare Centre Cost Distribution Plan

  • Writer: Swarup Dutta
    Swarup Dutta
  • Oct 28
  • 1 min read
Childcare Cost distribution chart
Childcare Cost distribution chart

CONSTRUCTION COST PLAN


Childcare Centre – 130 Places (3 Levels, Victoria)

Total GFA: ~2,298 sqm

Car Park: 29 spaces

Site Area: 1,766 sqm


🔹 ELEMENTAL COST BREAKDOWN (2025 ESTIMATE)

Element

Description

Unit Rate (AUD/sqm)

Area / Quantity

Cost (AUD)

% of Total

1. Substructure

Footings, ground slab, retaining walls

$350

780 sqm footprint

$273,000

6.2%

2. Superstructure

Frame (concrete & steel), upper floor slabs

$600

1,518 sqm upper floors

$910,800

20.6%

3. External Envelope

Walls, cladding, glazing, insulation

$650

2,298 sqm GFA

$1,493,700

33.8%

4. Roof

Colorbond/insulated flat roof, gutters

$250

780 sqm footprint

$195,000

4.4%

5. Internal Finishes

Partitions, doors, flooring, ceilings, paint

$500

2,298 sqm

$1,149,000

26.0%

6. Services (Electrical, Hydraulic, Fire, HVAC)

All mechanical, electrical, data & plumbing

$420

2,298 sqm

$965,160

21.8%

7. Fixtures, Fittings & Equipment (FFE)

Kitchen, joinery, cots, lockers, toilets

$280

2,298 sqm

$643,440

14.6%

8. External Works & Play Areas

Landscaping, fencing, play surfaces, soft fall

$310

862 sqm

$267,220

6.0%

9. Car Parking & Driveway

Asphalt, line marking, drainage

$800

29 spaces

$232,000

5.2%

10. Preliminaries, OH&P, Contingency

Builder prelims, supervision, insurance

12%

$669,500

15.2%

TOTAL CONSTRUCTION COST (excl. GST)




$6,798,820

100%

💰 Indicative Construction Rate: ≈ $2,960 / sqm GFA (typical for 3-storey centres in metro Victoria)

🔹 ADDITIONAL ALLOWANCES (OPTIONAL)

Item

Estimate (AUD)

Professional & Statutory Fees (8%)

$540,000

Furniture & Teaching Equipment

$180,000

Contingency (Design + Construction, 5%)

$340,000

TOTAL PROJECT BUDGET (incl. above)

≈ $7.86 million

🔹 COST SUMMARY BY CATEGORY

Category

Cost (AUD)

%

Building Construction

$6.80 M

86%

External Works & Carpark

$0.50 M

6%

Fees & Contingencies

$0.56 M

8%

TOTAL PROJECT COST

$7.86 M

100%


 
 
 